Molesey Weir

Molesey-Weir800px

Following a condition survey in 2010 the Environment Agency decided to rebuild Molesey Weir, which is located immediately south of Ash Island on the River Thames.

The project involved the complete reconstruction of the existing structure with new foundations, apron, stilling basin and gate supports. A new timber shingled canopy, supported on a steel frame, has replaced the old one and the existing fish trap was replaced with a new Larinier fish pass. The project included the design, supply, delivery to site, offloading, installation and commissioning of the weir.

The works were undertaken over two consecutive summers during the low flows on the river.

The first phase included:
• Installation of temporary works
• Scour protection downstream of the structure
• Installation of a temporary walkway
• Removal of existing apron and cutting down of existing steel sheet piles
• Construction of new mass concrete weir foundation and apron to accommodate four new radial gates
• Installation of four radial gates and a new walkway
• Building a new brickwork retaining wall
• M&E works

The second phase began in March 2014 and included:
• Installation of temporary works
• Construction of a new mass concrete weir foundation and apron
• Installation of two dipping radial gates and one radial gate
• Construction of a new fish pass
• M&E works
• Installation of a new walkway and new timber shingled canopy
• Installation of five timber guard piles and a bolina boom system
• Removal of the cofferdam and temporary walkway
• Provision of bird and bat boxes

Environmental research
The scheme offered an ideal opportunity to study the impact of our piling operations on several fish species in the Thames. Our staff tested the frequency of pilings as part of the research, while underwater vibration levels were taken and cross referenced with known thresholds affecting fish behaviour.

The results of this study can be directly applied to the control of high vibration construction activities, helping the recovery of flagship fish populations in the Thames.

Weir B is in close proximity to Ash Island and the project team engaged regularly with the residents to minimise the impact of the construction works. Echo barriers were installed on Ash Island to screen the noise from the piling operation and noise and vibration monitoring was carried out throughout the works.